Client: BAM Infra
Location: Rilland, Zeeland, the Netherlands
Execution period: September and October 2016 
Goal: accelerated consolidation of lower ground layers
Work method: vertical drainage

Facts and figures

  • Approx. 500,000 m vertical drainage installed (about 450 km in normal circumstances, about 50 km underneath high voltage cables)
  • Drain lengths 7.5 m (5.5 m high voltage cables)